DURA Bridge Provide Crossing to Indigeneous People at Ulu Kinta, Kinta District, Perak.

ulu kinta panaroma

Project:
To Construct a New Concrete Bridge with the Replacement of a Bailey Bridge and Other Associated Works at Kampung Ulu Kinta, Kinta District, Perak D.R.

(Membina Jambatan Konkrit Untuk Menggantikan Jambatan Bailey & Kerja-Kerja Berkaitan Di Kg. Ulu Kinta, Daerah Kinta, Perak D.R.)

Structure Type: Single span 32m long by 3.5m wide (MTB-R1) UHPdC integral beam-deck system.

Superstructure Feature: 2 pieces of DURA® TBG1325-32m

Substructure Feature: Pad Footing

Loading Type: Full HA+30HB loading (BD37/01)

Client: JKR Perak   JKR

Consultant: Dura Technology Sdn Bhd (in-house design)

Contractor: Afdzal Yamin Enterprise (Class E)

Contract Period: 2 months

Construction Period: 4 months

Construction Status: Completed

Existing steel bailey bridge at Ulu Kinta Site.
Existing steel bailey bridge at Ulu Kinta Site.
Abutments completed (11/08/2012).
Bridge site near Sultan Azlan Shah Dam.
Bridge site near Sultan Azlan Shah Dam.
Site is ready for beam launching.
Low loader transporting beams into the job site through a narrow access (11/08/2012)
First two segments arrived to job site (11/08/2012).
First two segments unloaded using a single 45 tonnes capacity mobile crane.
Lifting of last segment.
Two DURA beams nicely assembled off site and ready for post-tensioning.
Completion of post-tensioning work on two Dura beams (15/08/2012).
Crane operator getting ready for beam launching (02/09/2012)
Lifting of TBG1325-32m using a single unit 275 tonnes mobile crane.
Two DURA beams nicely seat on the abutments (02/09/2012)
Elevation view.
Bottom soffit view.
GI railing installed (06/10/2012).
GI railing installed (06/10/2012).
Road sealed.
Road Guard rail installed (10/12/12).
Completed Ulu Kinta bridge.
After 1 year.
After 1 year.
After 1 year.
Existing steel bailey bridge at Ulu Kinta Site.