2014 Projects

First Dura Composite Bridge Crossing Sungai Kurau

kurau 1 pana1
Project:
 Kerja-Kerja Membina Dan Pencegah Banjir Sungai Kurau Dari Pondok Tanjung Ke Hulu Sepanjang 4.88KM Serta Kerja Kerja Lain Yang Berkaitan, Dearah Larut Matang Dan Selama, Perak Darul Ridzuan (Bridge 2 - CH10080)

Structure Type: Single span 50m x 4.8m wide UHPC U-beam composite bridge

Superstructure Feature: 1 piece of DURA® UBG1750-50m topped with 180mm thk in-situ RC deck slab

Substructure Feature: 450mm dia. Spun Pile (Class B)

Loading Type: Full HA+30 unit HB loadings

Client: JPS Perak   jps

Consultant / Designer: Dura Technology Sdn Bhd

Contractor:  Harta Minda Sdn Bhd                  

Construction Status:  Completed 
Proposed new bridge site and existing old bridge (19/10/2013).
Piling in progress (19/10/2013).
Completion of piling work at abutment B (19/10/2013).
Unloading DURA U beam segments (30/10/2013).
All segments unloaded (30/10/2013).
Assembling 2nd U segment (16/01/2014).
Assembling 3rd U segment (16/01/2014).
Assembling 4th U segment (16/01/2014).
Assembling last 7th end segment (16/01/2014).
Full DURA UBG1750-50m assembled in one day (16/01/2014).
Casting of in-situ RC deck (15/02/2014).
Completion of bridge work (01/03/2014).
Sg Kurau bridge 1 (18/05/2014).
Sg Kurau bridge 1 (18/05/2014).
Proposed new bridge site and existing old bridge (19/10/2013).