Prefabricated DURA Bridge Assembled Overnight at Pangkor Island

Project: To Replace Teluk Raja Bayang Wooden Bridge at Pangkor Island, Route A205, Manjung District, Perak Darul Ridzuan. 
(Menggantikan Jambatan Kayu Teluk Raja Bayang Di Pulau Pangkor, Laluan A205, Daerah Manjung, Perak Darul Ridzuan.)

GPS Location: 4.21071N; 100.574758E

Structure Type: Single span 12m x 8.2m wide UHPC bridge

Superstructure Feature: 6 pcs of DURA® IB650-12.2m & 24 pcs of Customised DURA®  planks

Substructure Feature: No changed / maintained

Client: Jabatan Kerja Raya Perak   JKR

S.O.: JKR Manjung

Consultant: Concrete Technology Sdn Bhd

Contractor:

Contract Period: 6 months

Construction Status: Completed

Existing old Teluk Raja Bayang bridge.
Existing old Teluk Raja Bayang bridge.
Major steel beams badly corroded.
Uploading DURA I-beam to barge (24/03/2014).
Uploading DURA I-beam to barge (24/03/2014).
Uloading precast Dura plank to barge (24/03/2014).
Demolition of existing old steel bridge begin (5:15pm - 22/04/2014 ).
Transporation of first three DURA beams for installation (9:10pm - 22/04/2014).
A 16 tonnes capacity mobile was used to lift the first beam (10:00pm - 22/04/2014).
First three beams assembled with 45min (10.42pm - 22/04/2014).
Demolition of existing old steel bridge continue (10.:58pm - 22/04/2014 ).
Assembling of precast UHPC decks (12:07 - 23/04/2014).
Precast planks almost complete installation (7:04am - 23/04/2014).
Precast planks almost complete installation (7:19am - 23/04/2014).
All planks installed (7:53am - 23/04/2014).
New bridge open for traffic (8:33am - 23/04/2014).
A new Dura prefabricated bridge installed over night (8:34am - 23/04/2014).
A new Dura prefabricated bridge installed over night (8:34am - 23/04/2014).
Existing old Teluk Raja Bayang bridge.