2014 Projects

Replacement of Damaged Bridge Over Bukit Merah Dam

24
Project
: RTB Lembangan Sungai Kerian - Projek Menaiktaraf Jambatan Alur Limpah Selatan Di Empangan Bukit Merah Serta Kerja-Kerja Lain Yang Berkaitan Di Daerah Kerian, Perak Darul Ridzuan.

GPS Location: 5.030669N; 100.650887E

Structure Type: Multiple spans 55m x 9.5m wide UHPC composite bridge

Superstructure Feature: 12 pieces of DURA® IB650-13.3m & 18 pieces DURA® IB650-9.2m

Substructure Feature: No changed / maintained

Client: JPS Perak   jps

S.O.: JPS Daerah Kerian

Consultant: Concrete Technology Sdn Bhd (alternative design)

Contractor: Global Terbilang Sdn Bhd

Contract Period: 18 months

Construction Status: Completed

Existing Alur Limpah Selatan Bridge cross Bukit Merah Dam.
Existing bridge.
Existing bridge.
Some beams badly corroded.
Some beams badly corroded.
Transportating of precast DURA I-beams (16/04/2014).
Unloading of beams.
Unloading of beams.
First portion of the insitu decking constructed (29/08/2014).
First portion of the insitu decking constructed (29/08/2014).
Precast 20mm thick DURA left in-from used.
Precast 20mm thick DURA left in-from used.
Installation of precast RC parapet.
Second phase of beam launched. (29/12/2014)
Second phase of beam launched. (29/12/2014)
Final portion of the in-situ RC deck going to be casted (15/12/2014).
Completed new bridge with wearing surface laid.
Side view of the newly completed Bukit Merah Dam bridge.
Side view of the newly completed Bukit Merah Dam bridge.
Soffit view.
Completed after 2 years.
Completed after 2 years.
Completed after 2 years.
Completed after 2 years.
Existing Alur Limpah Selatan Bridge cross Bukit Merah Dam.