DURA Bridge Used at Canal of Mines Resort City, Selangor


Project
: To Construct A New RC Bridge at The Mines Resort City, Jalan Dulang, Seri Kembangan, Selangor Darul Ehsan.

GPS Location: 3.027921N; 101.71729E

Structure Type: Single span 22m long x 11.5m wide DURA composite bridge.

Superstructure Feature: 8 pieces of DURA IB650-22m

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 200mm RC Square pile (Grade40, Class 1)

Loading Type: Full HA + KEL loadings

Client: The Mines Resort City

Consultant: CYL Consult Sdn Bhd

Contractor: Mesa Engineering Sdn Bhd

Contract Period: 3 months

Status: Completed

Proposed site of new bridge over the canal of Mines Resort City.
The Mines canal.
Proposed new single span 22m long concrete bridge.
Construction of abutments in progress (05/06/2014).
RC abutments ready for beam launching (26/06/2014).
Lifting of first beam.
Lifting of second beam.
Lifting of fourth beam.
Four beams launched onto the RC abutments.
Four beams launched onto the RC abutments.
Completion of beam launching (26/06/2014).
Completion of beam launching (26/06/2014).
Completion of beam launching (26/06/2014).
Fixing temporary plank (05/07/2014).
Casting in-situ RC deck/slab (09/07/2014).
The completed Mines Canal Bridge.
The completed Mines Canal Bridge.
The completed Mines Canal Bridge.
The completed Mines Canal Bridge.
The completed Mines Canal Bridge.
The completed Mines Canal Bridge.
The completed Mines Canal Bridge.
Proposed site of new bridge over the canal of Mines Resort City.