2014 Projects

Second Dura Composite Bridge Crossing Sungai Kurau


Project:
Kerja-Kerja Membina Dan Pencegah Banjir Sungai Kurau Dari Hulu kolam Bukit Merah Ke Pondok Tanjung Sepanjang 8.4 km Serta Kerja Kerja Lain Yang Berkaitan, Dearah Kerian, Perak Darul Ridzuan (Bridge 1 Sg. Kurau CH.3336.5)

Structure Type: Single span 50m x 4.8m wide UHPdC U beam composite bridge

Superstructure Feature: 1 pieces of DURA® UBG1750-50m topped with 180mm thk in-situ RC deck slab

Substructure Feature: 450mm dia. Spun Pile (Class B)

Loading Type: Full HA+30 unit HB loadings

Client: JPS Perak   jps

Consultant: Dura Technology Sdn Bhd

Contractor: Aspasia Construction & Development S/B                                  

Construction Status: Completed

Signboard showing project detail.
Sungai Kurau.
Existing crossings.
Completion of piling work, maintain load test in progress (15/10/2013).
Newly assembled precast DURA U girder using intermediate support method (16/02/2014).
PT work officers get ready to install cable to the beam (16/02/2014).
Preparing timber formwork for RC decking (03/03/2014).
Preparing timber formwork for RC decking (03/03/2014).
Preparing timber formwork for RC decking (03/03/2014).
Newly completed single span DURA composite bridge crossing Sunga Kurau.
Newly completed single span DURA composite bridge crossing Sunga Kurau.
Newly completed single span DURA composite bridge crossing Sunga Kurau.
Signboard showing project detail.
01/12 
start stop bwd fwd



First Dura Composite Bridge Crossing Sungai Kurau

kurau 1 pana1
Project:
 Kerja-Kerja Membina Dan Pencegah Banjir Sungai Kurau Dari Pondok Tanjung Ke Hulu Sepanjang 4.88KM Serta Kerja Kerja Lain Yang Berkaitan, Dearah Larut Matang Dan Selama, Perak Darul Ridzuan (Bridge 2 - CH10080)

Structure Type: Single span 50m x 4.8m wide UHPC U-beam composite bridge

Superstructure Feature: 1 piece of DURA® UBG1750-50m topped with 180mm thk in-situ RC deck slab

Substructure Feature: 450mm dia. Spun Pile (Class B)

Loading Type: Full HA+30 unit HB loadings

Client: JPS Perak   jps

Consultant / Designer: Dura Technology Sdn Bhd

Contractor:  Harta Minda Sdn Bhd                  

Construction Status:  Completed 
Proposed new bridge site and existing old bridge (19/10/2013).
Piling in progress (19/10/2013).
Completion of piling work at abutment B (19/10/2013).
Unloading DURA U beam segments (30/10/2013).
All segments unloaded (30/10/2013).
Assembling 2nd U segment (16/01/2014).
Assembling 3rd U segment (16/01/2014).
Assembling 4th U segment (16/01/2014).
Assembling last 7th end segment (16/01/2014).
Full DURA UBG1750-50m assembled in one day (16/01/2014).
Casting of in-situ RC deck (15/02/2014).
Completion of bridge work (01/03/2014).
Sg Kurau bridge 1 (18/05/2014).
Sg Kurau bridge 1 (18/05/2014).
Proposed new bridge site and existing old bridge (19/10/2013).
01/14 
start stop bwd fwd



DURA Composite Bridge for Busy Road at Teluk Intan, Hilir Perak


Project:
Cadangan Menggantikan Pembentung Sediada, Melebarkan Jalan Dan Kerja-Kerja Di Laluan FT 058 Seksyen 3.50, Daerah Hilir Perak, Perak D.R.

Structure Type: Single span 8m x 17m wide UHPdC composite bridge.

Superstructure Feature: 22 pieces of DURA® UB650-8m

Substructure Feature: 450mm diameter spun piles (Class B)

Client: Jabatan Kerja Raya Malaysia   JKR 

Consultant: Jurutera Perunding Concrete Technology

Contractor: Belanti Wangsa (M) Sdn Bhd   belati wangsa

Status: Completed
Sungai Parit Selatan.
Existing old pipe culvert over Sg. Parit Selatan (31/03/2013)
FT058 road.
Lifting of light-weight DURA I beam (24/10/2013).
First phase of the new bridge open for traffic (14/12/2013).
First phase of the new bridge open for traffic (14/12/2013).
Flap gate installed (08/02/2014).
Second portion of the new bridge open for traffic.
Construction of last portion of the abutments.
Last batch of precast I beam launched (12/03/2014).
Premixing the road (11/04/2014).
Premixing the road (11/04/2014).
The completed bridge.
The completed bridge.
The completed bridge.
The completed bridge.
The completed bridge.
The completed bridge.