DURA Light-Weight Bridge System Used in Farm Area


Project
: Kerja Membina Semula Jambatan Parit Senin Rancangan Saliran Pertanian Senin Mukim Layang Layang, Daerah Perak Tengah, Perak Darul Ridzuan.  (Medium Traffic Bridge).


GPS Location: 4.392823N, 100.900432 E

Structure Type: Single Span 15m long x 6m wide DURA composite bridge

Superstructure Feature: 4 pieces of DURA® IB650-15m

Substructure Feature: 2 nos. of cast in-situ RC abutments

Foundation Feature: 200mm square RC piles (JKR Class 1)

Loading Type: HA + KEL loading + 30 Units HB Loadings (BD37/01)

Client: JPS Perak    jps

Consultant: N/A

Contractor: Anjung Kenari

Contract Period: 3 months

Construction Status: Completed       
Light weight DURA IB650-15m launched using single unit 45 tonnes mobile crane.
Light weight DURA IB650-15m launched using single unit 45 tonnes mobile crane.
Installation of DURA 25mm thick left in permanent formwork during mobile crane.
Installation of DURA 25mm thick left in permanent formwork during mobile crane.
Precast beams and left-in-formwork assembled within half day.
Soffit view of the bridge.
Kg Parit Senin bridge.
Completed after 6 months (27/03/2016).
Completed after 6 months (27/03/2016).
Completed after 6 months (27/03/2016).
Completed after 6 months (27/03/2016).
Light weight DURA IB650-15m launched using single unit 45 tonnes mobile crane.