New Bridge For Residents of Kg Banir, Tapah, Perak.

Kg Dato banir

Project
: To Construct Road from Kampung Banir to Access 1, Batang Padang District, Perak D.R. 

(Membina Jalan Dari Kampung Banir Ke Laluan 1, Daerah Batang Padang, Perak D.R.)

Structure Type: Single span 29m long x 13.9m wide (R5) UHPDC integral beam-deck system.

Superstructure Feature: 9 pieces of DURA TBG1325-29m

Substructure Feature: 600mm diameter bored piles

Loading Type: Full HA + 45HB loading (BD37/01)

Client: JKR Perak   JKR          Consultant: Perunding HJRS Sdn Bhd   hjrs

Contractor: F & C Communication S/B (Class A)

Contract Period: 24 months

Status: Completed

Project signboard and detail.
Existing old bridge.
Existing old bridge.
Bored piling construction in progress (20/06/2013).
Steel reinforcement for bore piles.
Unloading Dura beam to site (15/11/2013).
Nine beams unloaded to site (16/11/2013).
Strands installed for the precast T beams (25/04/2015).
Stressing of precast DURA beams in progress (15/01/2015).
Stressing of precast DURA beams in progress (15/01/2015).
Beam launching day (21/04/2015).
Lifting of DURA TBG1325-29m using two units 20 tons mobile cranes (21/04/2015).
Transporting beam to bridge site.
Lift of DURA TBG1325-29m using two units 45 tons mobile cranes.
Launching of last beam (22/04/2015).
9 nos. of TBG1325-29m launched and seated on abutments.
Soffit view of the newly launched beams.
Preparation of formwork for joint stitching work (12/05/2015).
A portable UHPC mixer is used to produce in-situ UHPC.
Measuring tape is used to ensure the T16 reinforcement has sufficient lapping length.
Placing of UHPC into the joint (14/05/2015).
UHPC placed at the joint formworks (14/05/2015).
A layer of plastic is sued to cover the freshly cast stitching joint (14/05/2015).
The completed Kg Banir Bridge (16/06/2015).
The completed Kg Banir Bridge (16/06/2015).
The completed Kg Banir Bridge (16/06/2015).
Project signboard and detail.