Login Form



2016 Projects

DURA Segmental T-Beams Used in Mountaineous Terrains


Project
: Menaiktaraf Jalan Dari Jalan Utama Kg Orang Asli Bawong-RPS Legap Ke Pos Perwor, Sungai Siput, Perak D.R. 
 
Nos. of Bridges: 2

GPS Location
: Bridge 1 (5.006644N; 101.241343 E); Bridge 3 (5.016283N; 101.264327 E)

Structure Type: Single Span 30m long x 10m wide DURA Integral Beam-Deck bridge

Superstructure Feature: 7 pieces of DURA® TBG1325-30m per bridge

Substructure Feature: 2 nos. of cast in-situ RC abutments per bridge

Foundation Feature: 300mm micropiles

Loading Type: HA + KEL loading + 30 Units HB Loadings (BD37/01)

Client: JKR Perak    JKR

Consultant: N/A

Contractor: HS Development Sdn Bhd

Contract Period: 18 months

Construction Status: Completed

Existing steel bridge 1.
Existing steel bridge 3.
Bridge 1: Site Clearing.
Bridge 3: Bar fitting for pile caps.
Bridge 3: Bar fitting for pile caps.
Bridge 1: Unloading beam segment for PT work (05/01/2016).
Bridge 1: Unloading beam segment for PT work (05/01/2016).
Bridge 1: Seven DURA TBG1325-30m assembled and ready for PT work (07/01/2016).
Bridge 3: Two units 25 tonnes used for uploading beam to trucks (17/03/2016).
Bridge 3: Two units 25 tonnes used for uploading beam to trucks (17/03/2016).
Bridge 3: One unit 45 tonnes and 1 unit 25 tonnes cranes used for beam launching (17/03/2016).
Bridge 3: Seven beams fully launched (18/03/2016).
Bridge 3: Seven beams fully launched (18/03/2016).
14
15
Completed Bridge 1.
Completed Bridge 3.
Existing steel bridge 1.