Construction of Light Traffic Bridge at Changkat Cermin

 
Project: To
Rebuilding Parit Besat Bakong, Agricultural Drainage Plan, Changkat Cermin, Mukim Bota, Perak Tengah District, Perak D.R.

(Membina Semula Parit Besat Bakong, Rancangan Saliran Pertanian, Changkat Cermin, Mukim Bota, Daerah Perak Tengah, Perak D.R.)
 
GPS Location: 4.333279N; 100.860325E

Structure Type: Single Span 35m x 6.5m Wide Composite Bridge System.

Superstructure Feature: 2 pieces of DURA® UBG1250-35m, with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 250mm RC Square Piles

Loading Type: HA+KEL Only (BD37/01)

S.O.: JPS Perak    jps

Consultant: Jurutera Perunding Concrete Technology

Contractor: Wangsa Wawasan

Contract Period: 4 months

Construction Status: Completed

Prepartion of timber formwork for pile cap casting.
Prepartion of timber formwork for pile cap casting.
Construction of temporary support for beam assembly purpose.
Lifting of centre segment using 120 tonnes mobile crane.
Centre segments positioned on temporary supports.
Centre segments positioned on temporary supports.
End segments positioned.
Lifting of last segment.
Two number of UBG1250-35m assembled.
Pushing strands into the corrugated ducts.
Post-tensioning work in progress.
Beam detached from temporary supported after tensioning.
Cutting of excessive strands.
Left-in formwork used prior-to casting of RC decking.
RC deck constructed.
RC deck constructed.
Prepartion of timber formwork for pile cap casting.