DURA Pedestrain Bridge Solution for Spillway of a Dam at Pahang


Project: To
Upgrading Dam Facility, Bridge Construction and Completion a Pedestrian Bridge (LTB) Crossing Spillway and Other Related Work at Anak Endau Dam, Pahang D.M.  

(Kerja-Kerja Menaiktaraf Fasiliti Empangan, Membina dan Menyiapkan Sebuah Jambatan Laluan Ringan (LTB) Merentasi Spillway dan Lain-lain Kerja Berkaitan di Empangan Anak Endau, Pahang D.M.).

GPS Location: 2.619706N, 103.437463E

Structure Type: Single Span 35m x 6.5m Wide Composite Bridge System.

Superstructure Feature: 1 pieces of DURA® UBG1250-36m, with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC Piers

Foundation Feature: 200mm RC Square Piles

Loading Type: 2 kPa SIDL and 5 kPa Live Load (BD37/01)

Client: JPS Pahang           S.O.: JPS Rompin    jps

Consultant: Jurutera Perunding Concrete Technology

Contractor: Generasi Teknik Sdn Bhd

Contract Period: 5 months (June 2016 – Oct 2016)

Construction Status: Completed

Spillway of Anak Endau Dam.
Spillway of Anak Endau Dam.
Spillway of Anak Endau Dam.
Temporary concrete support installed and ready for beam assembly.
Two segments assembled.
Lifting of the last segment using 45 tonens mobile crane.
Last segment assmebled.
A single span UBG1250-36m U girder assembled.
A single span UBG1250-36m U girder assembled.
Installation of strands into PT ducts.
Beam detached from temporary supports after post-tensioned.
Completed pedestrian bridge.
After 1 year.