Single Span 55m DURA Composite Bridge used at Tumpat, Kelantan


Project: Upgrading The Morak-Talent-Fourth Street [4] Tok Mek Ngah, Tumpat, Kelantan [Fasa 2].

(Menaiktaraf Jalan Morak-Kebakat-Cabang Empat [4] Tok Mek Ngah, Tumpat, Kelantan [Fasa 2].)

GPS Location: 6.147124N, 102.189201 E

Structure Type: Single Span 55m x 22.5m wide Composite Bridge System.

Superstructure Feature: 7 pieces of DURA® UBG2000-55m

Substructure Feature: 2 nos. of cast in-situ RC abutments

Foundation Feature: 500mm dia. Spun pile (Class B)

Loading Type: HA + KEL loading + 45 Units HB Loadings (BD37/01)

Client: Kerajaan Negeri Kelantan / JKR Kelantan    JKR

Consultant: Concrete Technology Sdn Bhd

Contractor: D’ Intan Trade Bina Sdn Bhd (G7)

Contract Period: 18 months

Construction Status: Completed
Sungai Batu Tampar bridge existing site.
Piling work is in progress.
Casting of abutment A in progress.
Unloading UBG2000 segment at open space (260516).
First beam DURA UBG2000-55m aligned (260516).
First beam DURA UBG2000-55m aligned (260516).
Three beams aligned.
Abutments A and B partially constructed.
2 units of 160 tonens mobile cranes parked behind the abutments and ready for beam launching (171016).
Lifting of first DURA UBG2000-55m.
Two U beams positioned (171016).
Six beams positioned (191016).
Lifting of last beams (191016).
Seven number of DURA UBG2000-55m launched (201016).
Side view of the new launched Tumpat bridge girders.
Construction of in-situ RC composite decking.
Construction of in-situ RC composite decking.
Construction of wingwall of abutment B.
Construction of approach slab.
Installation of precast parapets.
Newly finished single span 55M long fully-integral composite bridge.
Completed Bridge
Completed Bridge
Completed Bridge
Completed Bridge
Sungai Batu Tampar bridge existing site.