Dura Shallow Beams used at Residential Housing Project at Kuala Selangor


Project: To Build a New Bridge at the Project on the Construction of 315 Units 2 Storey High Terrance Houses (15’ x 55’) and 2 Units Compact Substations at Lots PT 1887, PT 1888, PT 1890, PT 1891, and PT 1892, Mukim Ijok, Kuala Selangor, Selangor.

 
(Membina Jambatan Baru di Projek Pembinaan 315 Unit Rumah Teres Mampu Milik 2 Tingkat (15’x55’) dan 2 Unit Compact Substation; Di Atas Lot PT 1887, PT 1888, PT 1890, PT 1891, Dan PT 1892, Mukim Ijok, Daerah Kuala Selangor, Selangor)

GPS Location: 3.238109 N, 101.476939 E

Structure Type: Single Spans 36m by 10.5m Wide Composite Bridge

Superstructure Feature: 4 pieces of DURA® UBG1250-36m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 400mm dia. Spun pile (Class B)

Loading Type: HA+KEL or 30 units HB loadings (BD37/01)

Client: Regency Land Sdn Bhd

S.O.: Perunding Majucipta Sdn Bhd

Consultant: JPCT (Alternative Design)

Contractor: Maltecon Builders Sdn Bhd

Construction Status: Completed        

Both RC abutments partially constructed and ready to receive precast beams.
Both RC abutments partially constructed and ready to receive precast beams.
Transporation of UBG1250 segments from the factory.
Unloading end segment using 45 tonnes mobile crane.
Unloading end segment using 45 tonnes mobile crane.
Two beams assembled near the bridge site.
DURA UBG1250 partially assembled.
Unloading PC strands.
Installation of PC strands.
Installation of strands into the ducts.
Stressing of UBG1250-36m in progress.
Cutting of access length of strands after PT work.
End plates of two beams patched with cement paste.
Preparation for beam launching.
Placing 1st U beam onto the steel transfer girders.
Positioning of first beam.
Positioning of third beam.
Completion of beam launching.
Formwork preparation for RC deck
Approach slab concrete preparation
Deck slab concrete in progress
Completed bridge.
Both RC abutments partially constructed and ready to receive precast beams.