Project: MEMPERELOKKAN JALAN TAIPING/SELAMA, DAERAH LARUT, MATANG DAN SELAMA, PERAK DARUL RIDZUAN. (FASA 2A :  KUBU GAJAH KE PENEMPATAN RANCANGAN BELIA PONDOK TANJUNG) Bridge 2- Sg Ijok       

GPS Location: 5.081517 N; 100.720305 E

Structure Type: Single span 50m long x 14m wide UHPC Composite Bridge System

Superstructure Feature: 3 pieces of DURA® UBG2000-49.5m

Substructure Feature: 500mm dia. spun pile (Class B)

Client: JKR Perak      JKR

S.O.: JKR Daerah Larut, Matang & Selama

Consultant: Jurutera Perunding Concrete Technology

Contractor: Solid Gold Synergy Sdn Bhd

Contract Period: 18 months

Construction Status: Under Construction       

Existing old bridge crossing Sg. Ijok.
Sg. Ijok.
Piling done at Abutment B (11/09/2014).
Construction of pile cap at abutment A (11/09/2014).
Unloading DURA UBG-50m segments (04/12/2014).
A single span DURA UBG-50m fully assembled off-site (04/12/2014).
Sg. Ijok bridge beam launching day (01/07/2015).
Lifting of 1st beam onto a truck.
Transporting first beam to the bridge site.
Launching the first beam to the abutment seatings.
First beam launched.
Lifting of 2nd beam.
Three DURA UBG2000-49.5m launched.
Three DURA UBG2000-49.5m launched.
Abutment A casted.
Preparation of timber formwork for deck casting.
Preparation of timber formwork for deck casting.
Preparation of timber formwork for deck casting.
Fixing reinforcement and formwork for Abutment B.
Steel reinforcment for the RC deck.
Completion of RC deck and RC parapet.
Laying of binder course at approach road.
Completion of Sg Ijok bridge.
Existing old bridge crossing Sg. Ijok.