Project: Membina Jambatan Konkrit Untuk Menggantikan Jambatan Bailey & Kerja-Kerja Berkaitan di Kg. Baru, Ulu Chemor, Daerah Kinta, Perak D.R.

Structure Type: Single span 30m long by 3.5m wide (MTB-R1) UHPdC integral beam-deck system.

Superstructure Feature: 2 pieces of DURA® TBG1325-29.5m

Substructure Feature: 200mm square RC piles

Loading Type: Full HA+30HB loading (BD37/01)

Client: JKR Perak   JKR

Consultant: Dura Technology Sdn Bhd (in-house design)

Contractor: Anjung Kenari (Class E)

Contract Period: 2 months

Construction Period: 3 months

Construction Status: Completed

Access road of Kg Baru, Ulu Chemor.
Existing bailey bridge.
Existing bailey bridge crossing a small river.
Condition of the bailey is not well.
RC piles were used as foundation support for the new bridge.
A single unit of 275 tonnes capacity mobile crane use to lift the precast beam.
Launching of beam 1 to the RC abutments.
Launching of beam 2.
Jointing ready for stitching.
Newly completed single span 30m Kg Baru Bridge.
Newly completed single span 30m Kg Baru Bridge.
Newly completed single span 30m Kg Baru Bridge.
Newly completed single span 30m Kg Baru Bridge.
After 3 months (07/10/2012).
After 3 months (07/10/2012).
After 3 months (07/10/2012).
After 15 months (10/10/2013).
Access road of Kg Baru, Ulu Chemor.