Project
: Cadangan Pembinaan Dermaga 300m Kedua CT6 dan Jambatan Penghubung di Pembangunan Perlabuhan Barat, Pulau Indah, Pelabuhan Klang, Klang Bandar di Raja Selangor Darul Ehsan untuk Westports Malaysia Sdn Bhd.

Structure Type: 5 spans of 13m long x 22.5m wide & 1 span 13m long x 40.5m wide DURA beam composite RC deck system.

Superstructure Feature: 102 pieces of DURA TBG1000-12.1m

Substructure Feature: 800mm diameter spun piles

Loading Type: Special oversize cargo loading (max payload of 3000 metric tonnes)

Client: Westport Malaysia   logo westport3          Consultant: HSS Engineering 

Contractor: Putra Perdana Construction Sdn Bhd   Putra Perdana Contruction Sdn Bhd

Contract Period: 2 months (supply)

Supply Status: Completed

Westport Site (26/04/2012).
Westport Malaysia wraft construction in progress (26/04/2012).
Driving of 800mm diameter spun piles (26/04/2012).
Existing excess bridge to the wharf.
Casting of pretension DURA TBG1000-12.1m precast beam using G150 ultra-high performance ductile concrete (07/04/2012).
After demould and transfer of prestressing (09/04/2012).
Destructive performance load test (ULS) of TBG1000-12.1m in flexural strength test, at P =1230 kN.
Destructive performance load test (ULS) of TBG1000-12.1m in shear strength test, at P =2140 kN.
Crack pattern of tested beam at flexure strength test (ULS).
DURA beams at stock yard (31/05/2012).
Dura beams uploaded to a truck and ready for transportation.
Lorries parked at Westport and waiting for beam launching (10/06/2012).
Launching of first beam to the first span using a single unit 60 tonnes mobile crane (09/06/2012).
Beam launching on the second span (10/06/2012).
A single unit 160 tonnes mobile crane was used to launched the beams for the second span (10/06/2012).
A portion of the concrete deck was constructed for span 1 and 2 (04/07/2012).
A unit of 160 tonnes crane sitting on the new cast deck (04/07/2012).
Beam launching for the fourth span (04/07/2012).
Four spans with RC decking completed (23/07/2012).
Beam launching for the fifth span (23/07/2012).
Beam launching for the fifth span (23/07/2012).
Piling in progress at the wharf area (03/08/2012).
Five spans RC decking completed (03/08/2012).
Five spans RC decking completed (03/08/2012).
Preparation for the final 6th span for RC deck concreting (03/08/2012).
Completed Bridge25.
A giant crawler crain sit on the newly built bridge.
Bottom soffit view of the 6th span.
Another view of the completed 6 spans UHPdC composite bridge.
Bridge 25 (10/01/2013).
Bridge 25 (10/01/2013).
Bridge 25 (10/01/2013).
Bridge 25 (10/01/2013).
Bridge 25 (10/01/2013).
Bridge 25 (10/01/2013).
After 1 year since completion (26/06/2013)
After 1 year since completion (26/06/2013)
After 1 year since completion (26/06/2013)
Westport Site (26/04/2012).