Project: To Repair & Rehabilitate Kampung Bermin Bridge at Jalan Pahang, Tapah, Batang Padan District, Perak D.R.

            
(Membaikpulih Jambatan Kampung Bermin, Jalan Pahang, Tapah, Daerah Batang Padang, Perak D.R.)

Structure Type: Single span 42m x 4.0m UHPdC composite bridge (MTB-R1).

Superstructure Feature: 1 pieces of DURA® UBG1750-42m topped with 150mm thk RC deck

Substructure Feature: 300mm square RC pile

Loading Type: Full HA+30HB loading (BD37/01)

Client: JKR Batang Padang (Perak)   JKR          Consultant: Dura Technology Sdn Bhd (in-house design)

Contractor: Gemilang Aisy Sdn Bhd (Class D)

Contract Period: 4 months

Status: Completed

Existing bridge wash away by flash flood eary this year.
Proposed job site.
Proposed job site.
Project information.
Preparation of temporary access road (04/12/2012).
Preparation of temporary access road (04/12/2012).
Preparation of temporary access road (04/12/2012).
Transportation of DURA U-beam segments (14/12/2012).
Unloading beam segments to site (15/12/2012).
Unloading beam segments to site (15/12/2012).
Pier ready to received precast beam (24/01/2013).
Both abutment and pier are ready.
Assembly first end segment of the beam (07/03/2013).
Post-tensioning of UBG1750-42m in progress (21/03/2013)
Inside view of the precast beam.
Completion of PT work (21/03/2013).
Fitting reinforcement for deck slab (30/03/2013).
First half of the in-situ deck slab completed (06/04/2013).
Completion of RC deck slab (15/04/2013).
Completion of wearing coarse (20/04/2013).
Completed Kg Bermin bridge.
Completed Kg Bermin bridge.
Completed Kg Bermin bridge.
Completed Kg Bermin bridge.
After half year (15/10/2013).
After half year (15/10/2013).
After half year (15/10/2013).
After half year (15/10/2013).
After half year (15/10/2013).
Existing bridge wash away by flash flood eary this year.