Staff Login



MALAYSIA BOLEH !!! - Dura Bridge Made from Malaysia Going to be Used in India


Project: Construction of Major Bridge across Sole Nalla on Latur – Nitur -  Nilanga – Balki – Road NH72K.


GPS Location: 18.256878N, 76.724448E

Structure Type
: 2 spans x 55.5 m long (total 111 m), Major Bridge across Sole Nalla

Superstructure Feature: Simply Supported Four (4) UHPC Box Girders for each span

Substructure Feature: RC Portal Piers

Foundation Feature: Eight (8) Drilled Piles for Each Foundation.

Loading Type: IRC Class Loadings.

Client: Maharashtra State Road Development Corporation.

S.O.: Valecha-SDPL JV, Áyoleeza Consultants Pvt. Ltd.

Consultant: Technology and Proof Consultant: Indian Institute of Technology (IIT), Bombay 

                     Indian Consultant: Shirish Patel and Associates      
                    
                     Malaysian Consultant: HSS Engineers  Sdn. Bhd.                       
Contractor: Shinde Developers Pvt. Ltd. logo shinde
Contract Period: 1 Years

Construction Status: On-going
Construction of foundation work in progress.
Drop- in hammer used to dig holes on the ground.
Installation of steel cage into the dug holes.
Steel cage installed.
Preparation of bore pile starter bars (160519).
Preparation of bore pile starter bars at the pier region (160519).
Construction of foundation work in progress.
1/6 
start stop bwd fwd

The Application of 60m Long DURA U Bridge at Hulu Besut

Project: To Construct A New Bridge From Kg. Pasir Akar To Kg. Durian Telor, Hulu Besut, Terengganu

(Projek Membina Jambatan Baru Dari Kg. Pasir Akar Ke Kg. Durian Telor, Hulu Besut, Terengganu)

 GPS Location: 5.639662 N; 102.499176 E

Structure Type: Three Spans UHPC Beam Composite In Situ Deck Bridge System: 40m + 60m +40m x 11.5m wide.

Superstructure Feature
: 3 pieces of DURA® UBG2500-60m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 800mm & 1000mm Diameter Bored Pile

Loading Type: BD 37/01 – HA+30HB & HA+45HB

Client: JKR Malaysia  JKR

S.O.: JKR Malaysia  JKR

Consultant
: JKR Malaysia  JKR

Contractor: SS Base Contractors Sdn Bhd

Contract Period: 24 months

Construction Status: Under Construction       

Project signboard (130219).
Current bridge site (130219).
Current bridge site with temporary bridge installed (130219).
Construction of abutment (130219).
Piling work in progress (130219).
Project signboard (130219).
1/5 
start stop bwd fwd

DURA First Contribution for DBKL on 49m Long Bridge at Jalan Jelatek

Project: Replacement Of The Old Concrete Bridge To New Concrete Bridge Crossing Klang River at Jalan Jelatek, Kuala Lumpur.
            
(Cadangan menggantikan jambatan konkrit sediaada kepada jambatan baru merentasi sungai kelang, di Jalan Jelatek , Kuala Lumpur.)

GPS Location: 3.1648208 N; 101.7347227 E

Structure Type: Single Span 49m by 29.15m (Avg.) Wide Composite Bridge System.

Superstructure Feature: 11 pieces of DURA® UBG1500-49m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC piers

Foundation Feature: N/A

Loading Type: HA+ 45 units HB loadings (BD37/01)

Client: Dewan Bandaraya Kuala Lumpur (DBKL)

S.O.: Dewan Bandaraya Kuala Lumpur (DBKL)

Consultant: Ranhill Consulting Sdn Bhd.

Contractor: Umech Construction Sdn Bhd

Contract Period: 2 years 6 months

Construction Status: Under Construction       

Project signboard and detail.
Existing bridge in Jalan Jelatek.
Underneath view of the existing old brige.
Project signboard and detail.
1/3 
start stop bwd fwd


© 2009-2019 by GPIUTMD