Login Form



Single Span UHPC Bridge for (Bridge 2) Bukit Gambir, Ledang Johor.

Project   : To Change a Narrow and Old bridge at KM 1.9, 3.3, 4.9 and 7.4 Jalan Sengkang, Bukit Gambir (J143), Ledang Johor, Johor Darul Takzim (Bridge 2).

(Cadangan Menggantikan Jambatan Sempit Di KM 1.9, 3.3, 4.9 Dan 7.4 Jalan Sengkang, Bukit Gambir (J143), Ledang Johor, Johor Darul Takzim)
 
GPS Location: 2.2421633 N; 102.6667053 E (Bridge 2)

Structure Type: Single Span UHPC I Beam Composite In Situ Deck Bridge System: 18m x 12.5m wide.

Superstructure Feature: 9 pieces of DURA® IBeam650-18m

Substructure Feature: 2 nos. of cast in-situ RC abutments and 2 nos. of cast in-situ RC piers.

Foundation Feature: 450mm dia. Spun pile (Class B)

Loading Type: HA + 30 units HB loadings (BD37/01)

Client: JKR Johor  JKR

S.O.: JKR  JKR

Consultant: Perunding Sejati Sdn Bhd

Contractor: Golden Kluang Sdn. Bhd.

Contract Period: 24 months

Construction Status: Under Construction       

600mm dia, spun piles used as foundation.
600mm dia, spun piles used.
Construction of abutments.
Bridge site.
Construction of abutments.
Abutment A.
600mm dia, spun piles used as foundation.
1/6 
start stop bwd fwd


Single Span UHPC Bridge used at Bukit Gambir (Bridge 1) , Johor

Project   : To Change a Narrow and Old bridge at KM 1.9, 3.3, 4.9 and 7.4 Jalan Sengkang, Bukit Gambir (J143), Ledang Johor, Johor Darul Takzim.

(Cadangan Menggantikan Jambatan Sempit Di KM 1.9, 3.3, 4.9 Dan 7.4 Jalan Sengkang, Bukit Gambir (J143), Ledang Johor, Johor Darul Takzim)

GPS Location: 2.2312473 N; 102.6607008 E (Bridge 1)

Structure Type: Single Span UHPC I Beam Composite In Situ Deck Bridge System : 18m x 12.5m wide.

Superstructure Feature: 9 pieces of DURA® IBeam650-18m

Substructure Feature: 2 nos. of cast in-situ RC abutments and 2 nos. of cast in-situ RC piers.

Foundation Feature: 300mm dia. Spun pile (Class B)

Loading Type: HA + 45 units HB loadings (BD37/01)

Client: JKR Johor   JKR

S.O.: JKR    JKR

Consultant: Perunding Sejati Sdn Bhd

Contractor: Golden Kluang Sdn. Bhd.

Contract Period: 24 months

Construction Status: Under Construction       

Demolition and site clearing work.
Piling of 60mm spun pile.
Bridge site.
Piling work completed.
Demolition and site clearing work.
1/4 
start stop bwd fwd


Five Spans UHPC Composite Bridge from Kg. Seberang Manong to Pekan Manong


Project: To Construct Bridge at Sungai Perak from Kg. Seberang Manong to Pekan Manong (Kampung Simpang Melembu), Kuala Kangsar, Perak Darul Ridzuan


(Membina Jambatan Menyeberang Sungai Perak di antara Kampung Seberang Manong ke Pekan Manong (Kampung Simpang Melembu), Kuala Kangsar, Perak Darul Ridzuan)

GPS Location: 4.598792N; 100.881463E

Structure Type: Five Spans UHPC Beam Composite In Situ Deck Bridge System: 45m + 70m + 70m + 70m + 45m x 11.5m wide.

Superstructure Feature: 9 pieces of DURA® UBG3000-70m and 6 pieces of DURA® UBG2250-45m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 600mm dia. Spun pile (Class B)

Loading Type: LM1 + LM3 SV80

Client: JKR Malaysia JKR                            S.O.: JKR Perak  JKR 

Desinger: JKR Malaysia  JKR

Contractor: Kumpulan Awambina Sdn Bhd

Contract Period: 24 months

Construction Status: Under Construction

Original site
The bridge project site crossing to Sungai Perak.
Original site
The bridge project site crossing to Sungai Perak.
Original site
1/2 
start stop bwd fwd


© 2009-2015 by GPIUTMD