Five Spans UHPC Composite Bridge from Kg. Seberang Manong to Pekan Manong


Project: To Construct Bridge at Sungai Perak from Kg. Seberang Manong to Pekan Manong (Kampung Simpang Melembu), Kuala Kangsar, Perak Darul Ridzuan


(Membina Jambatan Menyeberang Sungai Perak di antara Kampung Seberang Manong ke Pekan Manong (Kampung Simpang Melembu), Kuala Kangsar, Perak Darul Ridzuan)

GPS Location: 4.598792N; 100.881463E

Structure Type: Five Spans UHPC Beam Composite In Situ Deck Bridge System: 45m + 70m + 70m + 70m + 45m x 11.5m wide.

Superstructure Feature: 9 pieces of DURA® UBG3000-70m and 6 pieces of DURA® UBG2250-45m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 600mm dia. Spun pile (Class B)

Loading Type: LM1 + LM3 SV80

Client: JKR Malaysia JKR                            S.O.: JKR Perak  JKR 

Designer: JKR Malaysia  JKR

Contractor: Kumpulan Awambina Sdn Bhd

Contract Period: 24 months

Construction Status: Under Construction

Original site
The bridge project site crossing to Sungai Perak.
Construction of temporary platform in prgress.
Temporary bridge
Temporary bridge under installation
Abutment A.
Pier 1.
Pier 2 under construction.
Installation of launching platform in progress.
First DURA UBG3000-70m.
Post-tensiong mock up on the UBG3000-70m.
Full mockup on post-tensioning work of DURA UBG3000-70m.
Unload and assembly of first DURA UBG2250 segment.
Unloading and assembly of U segments.
Installation of strands.
External tendons and ducting.
JD JPR Muar witnessing the progress work during beam launching (160918).
Cutting of extra strands after PT.
Tendons installed and post-tensioned.
Prepation of temporary staging for UBG3000-70m beam assembly.
Prepation of temporary staging for UBG3000-70m beam assembly (280918).