Login Form



New Triple Spans Bridge at Jalan Pasir Hor Crossing Sg. Seribong


Project: To Construct Three Spans Bridge at Jalan Pasir Hor, Kubang Kerian Ke Pasir Jelatang, Pasir Tumboh, Kota Bharu, Kelantan.


(Menaiktaraf Jalan Pasir Hor, Kubang Kerian Ke Pasir Jelatang, Pasir Tumboh, Kota Bharu, Kelantan)
 
GPS Location: 6.073648 N, 102.265898 E

Structure Type: Three Spans 30o Skew UHPC Beam Composite In Situ Deck Bridge System : 24m + 50m + 24m x 12m wide.

Superstructure Feature: 6 pieces of DURA® UBG1750-24m and 3 pieces of DURA® UBG1750-50m with Cast In-Situ RC Deck

Substructure Feature: 2 nos. of cast in-situ RC abutments and 2 nos. of cast in-situ RC piers.

Foundation Feature: 600mm dia. Spun pile (Class B)

Loading Type: HA + 45 units HB loadings (BD37/01)

Client: JKR Kelantan  JKR
S.O.: JKR  JKR

Consultant: Just Consult

Contractor: Yusri Maju Sdn. Bhd.

Contract Period: 24 months

Construction Status: Under Construction

Original site.
600mm spun piles at site
Pilling work in progress
Abutment A
Abutment B
Construction of abutment A
Substructure consturction in progress.
Substructure consturction in progress.
Cofferdam used to construction pier 2.
Unloading to site for assembly.
Three U-beams assembled.
Three U-beams assembled behind the abutments.
Beam launching in progress (140718).
Beam launching in progress (140718).
All beams launched (160718).
All beams launched (160718).
Original site.
01/16 
start stop bwd fwd


DURA Bridge Used in the State of Terengganu


Project: To Construct Jalan Terengganu By-Pass, Kuala Terengganu, Terengganu Darul Iman (Bridge ST3)


(Membina dan Menyiapkan Jalan Terengganu By-Pass, Kuala Terengganu, Terengganu Darul Iman) (Jambatan ST3)

GPS Location: 5.304631 N, 103.124018 E

Structure Type: Five Spans 38m by 11.5m Wide (Left & Right) Composite Bridge System.

Superstructure Feature: 20 pieces of DURA® UBG2000-38m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments and piers

Foundation Feature: 500mm dia. Spun pile (Class B)

Loading Type: Combination of HA+KEL or 45 units HB loadings (BD37/01)

Client: JKR Malaysia       JKR               S.O.: JKR Terengganu    JKR

Consultant: Jannacks Consultants Sdn Bhd

Contractor: Iswarabena Sdn Bhd Sdn Bhd (G7)

Construction Status: Under Construction  
Abutment A and pier 1.
RC columns of pier 1.
Pile loading test at pier 2.
Piling work in progress at pier 3.
Pier 1 done.
Pier A done.
Transporting U beam segments.
Unloading and assembly of U beams.
18 numbers of U beam assmebled at a open space.
Installation of strands in progress.
Anchor plates installed.
Storage space of precast U beams.
Abutments A and Piers 1 constructed.
Piers 2.
Construction of pile cap of Pier 3.
PT work in progress.
Pressure gauge of jack.
Segments detached from temporary intermediate supports.
Cross head formwork preparation at pier 3.
Four U beams positioned on Abutment A and Pier 1
Four beams launched
All substructure components completed.
Continuation of beam launching for span 3.
Continuation of beam launching for span 3.
Transportation of beam 1 for span 3 (020218)
Beam lifting.
Positioning of second beam of span 3.
2 beams launched for span 4(030218).
3 beams launched for span 4(030218).
12 beams all launched (050218)
12 beams all launched (050218)
12 beams all launched (050218)
12 beams all launched (050218)
12 beams all launched (050218)
12 beams all launched (050218)
Abutment A and pier 1.
01/35 
start stop bwd fwd

DURA Bridge Used in the State of Terengganu


Project: To Construct Jalan Terengganu By-Pass, Kuala Terengganu, Terengganu Darul Iman (Bridge ST1)


(Membina dan Menyiapkan Jalan Terengganu By-Pass, Kuala Terengganu, Terengganu Darul Iman)

GPS Location: 5.283102 N, 103.141787 E

Structure Type: Five Spans 35m by 11.5m Wide (Left & Right) Composite Bridge System.

Superstructure Feature: 20 pieces of DURA® UBG2000-35m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments and piers

Foundation Feature: 500mm dia. Spun pile (Class B)

Loading Type: Combination of HA+KEL or 45 units HB loadings (BD37/01)

Client: JKR Malaysia    JKR               S.O.: JKR Terengganu    JKR

Consultant: Jannacks Consultants Sdn Bhd

Contractor: Iswarabena Sdn Bhd Sdn Bhd (G7)  iswarabena logo

Construction Status
: Under Construction        

Backfilling work and construction of RE walls at abutment A.
Piling work in progress at pier 3 and construction of pile cap at pier 4.
Backfilling and construction of RE wall at  Abutment B.
Construction of RC column for pier 2.
Pier 4 done.
Abutment B done.
Construction of pier 3.
Abutment A done with partial completed RE walls.
Pier 2 done.
Construction pier 3 portal frame.
Construction of pier 4.
DURA UBG2000-35m ready for beam launching.
Beam launching conducted at night time.
Beam launching conducted at night time.
Six U beams were launched.
Six U-beams were positioned.
Six number of precast U-beams where positioned.
Two spans with RC decking completed.
Two spans with RC decking completed.
Remaining 12 beams assembled near sites.
DURA beams ready for launching.
Prepartion work for beam launching.
Prepartion work for beam launching.
Last six spans ready for beam launching.
One unit of 200t and one unit of 300t mobiles geeting ready for beam launching.
Launching of first beam
Towing the second beam.
Four beams launched.
Eight beams launched.
12 beams fully launched onto peirs.
12 beams fully launched.
12 beams fully launched.
Backfilling work and construction of RE walls at abutment A.
01/32 
start stop bwd fwd


© 2009-2018 by GPIUTMD