Login Form



DURA Bridge Used in the State of Terengganu


Project: To Construct Jalan Terengganu By-Pass, Kuala Terengganu, Terengganu Darul Iman (Bridge ST1)


(Membina dan Menyiapkan Jalan Terengganu By-Pass, Kuala Terengganu, Terengganu Darul Iman)

GPS Location: 5.283102 N, 103.141787 E

Structure Type: Five Spans 35m by 11.5m Wide (Left & Right) Composite Bridge System.

Superstructure Feature: 20 pieces of DURA® UBG2000-35m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments and piers

Foundation Feature: 500mm dia. Spun pile (Class B)

Loading Type: Combination of HA+KEL or 45 units HB loadings (BD37/01)

Client: JKR Malaysia    JKR               S.O.: JKR Terengganu    JKR

Consultant: Jannacks Consultants Sdn Bhd

Contractor: Iswarabena Sdn Bhd Sdn Bhd (G7)  iswarabena logo

Construction Status
: Under Construction        

Backfilling work and construction of RE walls at abutment A.
Piling work in progress at pier 3 and construction of pile cap at pier 4.
Backfilling and construction of RE wall at Abutment B.
Construction of RC column for pier 2.
Pier 4 done.
Abutment B done.
Construction of pier 3.
Abutment A done with partial completed RE walls.
Pier 2 done.
Construction pier 3 portal frame.
Construction of pier 4.
DURA UBG2000-35m ready for beam launching.
Beam launching conducted at night time.
Beam launching conducted at night time.
Six U beams were launched.
Six U-beams were positioned.
Six number of precast U-beams where positioned.
Two spans with RC decking completed.
Two spans with RC decking completed.
Remaining 12 beams assembled near sites.
Backfilling work and construction of RE walls at abutment A.
01/20 
start stop bwd fwd

Dura UHPFRC Makes Singaporean Precast Bathroom Unit (PBU) Lighter, Watertight, More Durable and Affordable


Project: Panorama - Proposed
Condominium Housing Development Comprising 4 Blocks of 17-storey, 2 Blocks of 20-storey Residential Building Total 698 Units with Swimming Pool, Landscape Deck, Communal Facilities and 2 Basement Carparks on Lot 17828 MK18 at Ang Mo Kio Avenue 2 (Ang Mo Kio Planning Area), Singapore.

GPS Location: 1.375742N; 103.834388 E

Product Type: 1015 pieces Customised Lithe - DURA UHPFRC Precast Bathroom Unit (PBU) Carcass

Client: Pinehill Investments Pte Ltd c/o Wheelock Properties 501 Orchard Road #11-01 Wheelock Place Singapore 238880

Consultant: TBA
Contractor: Tiong Seng Contractors (Pte) Ltd      TS Logo
Contract Period: 2015 – 2016

Construction Status: Completed
 


The Panorama, Ang Mo Kio Avenue, Singapore.
Google earth view of Panorama.
During construction.
During construction.
Dura UHPFRC precast bathroom carcass.
DURA PBU with interior finishes.
Dura PBUs - Lithe at Robin Village precast facility.
The Panorama, Ang Mo Kio Avenue, Singapore.
1/7 
start stop bwd fwd

New Sturdy Bridge for "Washed Away" Kampung Sawa Bridge During 2014/2015 Massive Flood


Project: To Construct a New Bridge In Kampung Sawa, and Related Works, Hulu Perak District, Perak D.R. (Post Flood). (PERS/752/2015)


(Membina Jambatan Baru Di Kampung Sawa, Dan Kerja-Kerja Yang Berkaitan, Daerah Hulu Perak, Perak D.R. (Pasca Banjir). (PERS/752/2015)


GPS Location: 5.210554 N, 101.071142 E

Structure Type: Four Spans 45m+45m+55m+35m x 5m Wide Composite Bridge System.

Superstructure Feature: 2 pieces of DURA ® UBG2000-45m, 1 piece of DURA ® UBG2000-55m, 1 piece of DURA ® UBG2000-35m, with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments and RC piers

Foundation Feature: 300mm dia. micropiles

Loading Type: HA+KEL or 30 units HB loadings (BD37/01)

Client: KKLW    Logo KKLW                         S.O.: JKR Hulu Perak    JKR

Consultant: N/A

Contractor: Lumut Project Management Sdn Bhd

Contract Period: 24 months (from 18 Jan 2016 to 18 Jan 2018)

Construction Status: Under Construction
Existing bridge at Kampung Sawa was destroyed by the year 2014 Dec massive flood.
Existing bridge at Kampung Sawa was destroyed by the year 2014 Dec massive flood.
Existing bridge at Kampung Sawa was destroyed by the year 2014 Dec massive flood.
Existing bridge at Kampung Sawa was destroyed by the year 2014 Dec massive flood.
Project signboard and detail.
Demolition of existing concrete bridge.
Demolition of existing concrete bridge.
8 points of micropile constructed at Abutment A.
Construction of 10 points of micropiles at Pier 1.
Setting out micropiles location for Pier 2.
Partially constructed pier 2.
Partially constructed substructures.
Transportation of UBG2000 girder segments.
Two segments positioned.
Six segments for second span positioned.
Positioning of end segment for first span.
Two numbers of UBG2000-45m already post-tensioned.
Two numbers of UBG2000-45m already post-tensioned.
Existing bridge at Kampung Sawa was destroyed by the year 2014 Dec massive flood.
01/18 
start stop bwd fwd




© 2009-2018 by GPIUTMD