Login Form



Single Span UHPC Bridge at Ulu Lawin, Perak


Project: To Construct Bridge at Ulu Lawin, Daerah Hulu Perak, Gerik, Perak Darul Ridzuan.


 (Membina Jambatan Ulu Lawin, Daerah Hulu Perak, Gerik, Perak Darul Ridzuan).

 GPS Location: 5.300921 N; 101.052175 E 

Structure Type: Single Span UHPC Beam Composite In Situ Deck Bridge System : 18m x 4m wide.

Superstructure Feature: 3 piece of DURA® IB650-18m with Cast In-Situ RC Deck

Substructure Feature: 2 nos. of cast in-situ RC abutments

Foundation Feature: 200mm x 200mm RC pile.

Loading Type: HA+KEL or 30 units HB loadings

Client: Pejabat Daerah Dan Tanah, Hulu Perak, Gerik Perak

S.O.: Jurutera Daerah , JKR Daerah Perak JKR

Consultant
: Jurutera Perunding Concrete Technology

Contractor: FD Construction and Supplier

Contract Period: : 3 Months

Construction Status: Under Construction
Sg Lawin.
RC square pile used as foundation.
RC piles installed.
Construction of RC abutments.
Abutments done and ready for beam launching.
Sg Lawin.
1/5 
start stop bwd fwd


Single Span Bridge at Kemuning Machang


Project: To Construct Bridge at Kg. Kemuning, Machang, Kelantan.


(Projek Membina Jambatan Dari Kg Kemuning Ke Pangkal Kuang, Kemuning, Machang, Kelantan).

GPS Location: 5.751480 N; 102.2061310E

Structure Type: Single Span 23m by 4m Wide Composite Bridge System.

Superstructure Feature: 3 piece of DURA® IB850-23m with Cast In-Situ RC Deck

Substructure Feature: 2 nos. of cast in-situ RC abutments

Foundation Feature: 200mm Sq RC Pile. 

Loading Type: Combination HA + 30HB Unit
 
Client: Kementerian Kemajuan Luar Bandar & Wilayah  Logo KKLW

S.O.: Kementerian Kemajuan Luar Bandar & Wilayah  Logo KKLW

Consultant: MZMS Consultant

Contractor: JLE Jalinan Ilham Enterprise

Contract Period: 3 Months

Construction Status: Under Construction

Proposed new bridge at Kg Kemuning.
Construction of RC abutments at river bank.
Construction of RC abutments.
Transportation of three number of DURA IB650-23m using low loader.
Reversing beam for beam launching.
45 tonnes capacity mobile crane used for beam launching.
Lifting of beam 1.
Positioning beam 2.
Lifting of last beam.
Placing left-in formworks.
All left-in formworks positioned.
Proposed new bridge at Kg Kemuning.
01/11 
start stop bwd fwd


Partial UHPFRC Box Girder Design Used at Eight Spans Bridge at Kampung Lambor Crossing Sg. Perak

  
Project: To Construct Bridge at Lambor (Crossing Sungai Perak).


(Membina Jambatan Menghubungkan Kg. Lambor Kiri Ke Kg. Lambor Kanan (Merentasi Sg. Perak).

GPS Location: 4.269773 N, 100.901552 E

Structure Type: Eight Span 404m by 11.5m Wide Composite Bridge System.

Superstructure Feature: 8 piece of DURA® GUBG2000-50m with Cast In-Situ RC Deck

Substructure Feature
: Cast in-situ RC abutments

Foundation Feature: 600mm dia. Spun Pile (Class B). 

Loading Type: LM1 & LM3 (SV100)

Client: Jabatan Kerja Raya Malaysia  JKR
S.O.: JKR Daerah Perak Tengah   JKR

Consultant: JKR Malaysia JKR

Contractor: Everfine Resources Sdn Bhd

Contract Period: 24 Months

Construction Status:  Under Construction
Project Signboard.
Original site at Lambor.
Original site at Lambor.
Project Signboard.
1/3 
start stop bwd fwd