2019 Projects

Replacement of 57 Years Old Bridge Project at Sungai Raia, Kinta


Project: To Construct Bridge at Sungai Raia, FT001/583/20, Kinta, Perak.

 
(Menggantikan Jambatan Sungai Raia, FT001/583/20, Kinta, Perak)

GPS Location: 4.51582 N; 101.13747 E

Structure Type: Single Span 50m by 11m Wide Composite Bridge System.

Superstructure Feature: 3 pieces of DURA® UBG1750-50m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 300mm dia. Micro Pile.

Loading Type: SV100 loadings (BS EN 1991-2-2003)

Client: Jabatan Kerja Raya Malaysia   JKR                 S.O.: JKR Daerah Kinta JKR

Consultant: Primareka Consultants  prima reka                  Contractor: Dura Construction Sdn Bhd  4 DURA Construction 2

Contract Period
: 24 months

Construction Status
: Completed

Project signboard for Sg. Raia Bridge
Existing Sg Raia Bridge.
Existing old bridge.
Micropiles used as foundation.
Maintain load testing in progress.
Construction of micropiles at abutment B completed (011018).
Lifing of DURA IB650-24m for the utility beams (141018).
Two numbers of DURA-IB650 was positioned.
Installation of precast DURA thin plank.
Two beams and precast DURA planks fully installed in half day.
Hacking of the existing old bridge (221018).
Hacking work in progress (221018).
Lifting of the first U-beam.
Assembly of UBG1750 segments.
Assembly of UBG1750 segments.
In-situ RC deck slab constructed.
Apporach slab constructed.
Approach road soon will be ready.
Sg Raia bridge temporary open for traffic (280519).
Sg Raia bridge temporary open for traffic (280519).