Replacement Bridge at Kg. Bagan Lawin using Single Spans

Project: To Replace A Collapse Bridge at Kampung Bagan Lawin, Daerah Hulu Perak, Perak

(Cadangan Membina Jambatan Kampung Bagan Lawin, Daerah Hulu Perak, Perak)

GPS Location: 5.292316 N; 101.061059 E

Structure Type
: Single Spans UHPC Beam Composite in-situ Deck Bridge System: 13m x 4.5m wide.

Superstructure Feature
: 2 pieces of DURA® IB650-13m with Cast In-Situ RC Deck

Substructure Feature: 2 nos. of Cast in-situ RC abutments

Foundation Feature: 200mm & 200mm RC Pile

Loading Type: HA+KEL or 30 units HB loadings

Client: Jabatan Tanah Gerik

S.O.: Jabatan Tanah Gerik

Consultant: JPCT

Contractor: MAE Equity

Contract Period: 3 months

Construction Status: Completed       

RC piles installed.
Access road to the bridge (061119).
Beam and UHPC left-in formwork fully installed.
Installation of dura UHPC railing
Completed bridge
Completed bridge
Completed bridge