New Extension and Widening of Batu Kawan Bridge 1 using Dura


Project: New Extension and Widening of Road Bridge of Sungai Jawi  (Bridge 1) 
             
(Pelebaran Jambatan Batu Kawan Sediada Merentasi Sungai Jejawi Di Batu Kawan Seberang Perai Selatan, Pulau Pinang.)

GPS Location: 5.2651550, N; 100.4390400 E

Structure Type: Multiple Span 211m by 40m Wide Composite Bridge System.

Superstructure Feature: 24 pieces of DURA® UBG1500-43.5m and 16 pieces of DURA® UBG1500-37.25m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC piers

Foundation Feature: Spun Pile 450mm

Loading Type: HA+ KEL & 45 units HB loadings (BD37/01)

Client: Penang Development Corporation (PDC)

S
.O.: Jabatan Kerja Raya (JKR)  JKR

Consultant: M.E.I Consultants Sdn Bhd.

Contractor: Zibina Jaya Sdn Bhd

Contract Period:

Construction Status: Under Construction
Existing concrete bridge crossing Sungai Jawi.
Exisiting bridge.
Existing bridge.
Soffit view of existing bridge.
Existing concrete bridge.
Transporting of U segments to site.
Unloading of U-segment.
Align beam segments.
14 beams assembled.
14 beams aligned.
14 beams aligned.
Post tensioning work in progress (290918).
All beams fully grouted into the ducts.
Spun pile used as foundation.
Abutment A.
Pier 1.
Construction of substructures on going.
Substructure work in progress.
Completion of substructure work and ready for beam launching.
Existing concrete bridge crossing Sungai Jawi.
01/19 
start stop bwd fwd

Replacement Bridge at Main Road to Kg. Pahat using Single Span UHPFRC


Project   : To Replace Bridge at Main Road to Kg. Pahat, Daerah Hulu Perak, Gerik, Perak.


 
(Membaikpulih Jambatan Jalan Utama Kg.Pahat, Daerah Hulu Perak, Gerik, Perak Darul Ridzuan )

 
GPS Location: 5.4949310 N; 101.1214160 E

Structure Type: Single Span UHPFRC Composite In-Situ Deck Bridge System : 12m x 4m wide.

Superstructure Feature: 3 pieces of DURA® IB650-12m with Cast In-Situ Grade40 RC Deck.

Substructure Feature: 2 nos. of cast in-situ RC abutments.

Foundation Feature: 200mm x 200mm Square RC pile.

Loading Type: HA+KEL or 30 units HB loadings

Client: Jabatan Tanah Gerik

S.O.: Jabatan Tanah Gerik

Consultant: JPCT

Contractor: SADAN WORKS ENTERPRISE

Contract Period: 3 Months

Construction Status: Completed        

Driving of RC piles.
PDA test.
Completion on driving of RC pile at one abutment.
Construction of pile cap.
Pile cap concreted.
Unload beams.
Beam launching.
Three I-beams positioned.
Installation of left-in formwork.
Beam and formwork fully installed.
Installation of RC deck reo and formworks.
Completed Kg Pahat Bridge.
Completed Kg Pahat Bridge.
Driving of RC piles.
01/13 
start stop bwd fwd

Dura UHPC Single Span Kg. Pahit, Gerik


Project   : To Replace Bridge at Main Road to Kg. Pahit, Daerah Hulu Perak, Gerik, Perak.


(Membaikpulih Jambatan Jalan Utama Kg.Pahit, Daerah Hulu Perak, Gerik, Perak Darul Ridzuan )

GPS Location: 5.585917 N; 101.057400 E

Structure Type: Single Span UHPC Beam Composite In Situ Deck Bridge System : 12m x 4m wide.

Superstructure Feature: 3 pieces of DURA® IBeam650-12m with Cast In-Situ RC Deck.

Substructure Feature: 2 nos. of cast in-situ RC abutments.

Foundation Feature: 200mm x 200mm RC pile.

Loading Type: HA+KEL or 30 units HB loadings

Client: Jabatan Tanah Gerik

S.O.: Jabatan Tanah Gerik

Consultant: JPCT

Contractor: MAINTENANCE N FAR

Contract Period: 3 Months

Construction Status: Under Construction
Driving of RC piles
Construction of abutments
Beam launching in progress (190918).
Third beam positioned.
Completion of beam launching (190918).
Placement of left-in formwork.
Apporach road constructed (021018).
Kg Pahit bridge (021018).
Completed Kg Pahit bridge.
Completed Kg Pahit bridge.
Completed Kg Pahit bridge.
Completed Kg Pahit bridge.
Completed Kg Pahit bridge.
Driving of RC piles
01/13 
start stop bwd fwd

Single Span UHPC Bridge at Ulu Lawin, Perak


Project: To Construct Bridge at Ulu Lawin, Daerah Hulu Perak, Gerik, Perak Darul Ridzuan.


 (Membina Jambatan Ulu Lawin, Daerah Hulu Perak, Gerik, Perak Darul Ridzuan).

 GPS Location: 5.300921 N; 101.052175 E 

Structure Type: Single Span UHPC Beam Composite In Situ Deck Bridge System : 18m x 4m wide.

Superstructure Feature: 3 piece of DURA® IB650-18m with Cast In-Situ RC Deck

Substructure Feature: 2 nos. of cast in-situ RC abutments

Foundation Feature: 200mm x 200mm RC pile.

Loading Type: HA+KEL or 30 units HB loadings

Client: Pejabat Daerah Dan Tanah, Hulu Perak, Gerik Perak

S.O.: Jurutera Daerah , JKR Daerah Perak JKR

Consultant
: Jurutera Perunding Concrete Technology

Contractor: FD Construction and Supplier

Contract Period: : 3 Months

Construction Status: Completed
Sg Lawin.
RC square pile used as foundation.
RC piles installed.
Construction of RC abutments.
Abutments done and ready for beam launching.
Transportation of Dura I-beam to site and ready for beam launching (110618).
Three I-beams launched on to abutments.
Installation of left-in formwork onto DURA I-beams.
Construction of In-situ RC decking (060918).
Completion of Ulu Lawin bridge(021018).
Completion of Ulu Lawin bridge(021018).
Completion of Ulu Lawin bridge(021018).
Completion of Ulu Lawin bridge(021018).
Completion of Ulu Lawin bridge(021018).
Sg Lawin.
01/14 
start stop bwd fwd

Single Span Bridge at Kemuning Machang


Project: To Construct Bridge at Kg. Kemuning, Machang, Kelantan.


(Projek Membina Jambatan Dari Kg Kemuning Ke Pangkal Kuang, Kemuning, Machang, Kelantan)

GPS Location: 5.751480 N; 102.2061310E

Structure Type: Single Span 23m by 4m Wide Composite Bridge System.

Superstructure Feature: 3 piece of DURA® IB850-23m with Cast In-Situ RC Deck

Substructure Feature: 2 nos. of cast in-situ RC abutments

Foundation Feature: 200mm Sq RC Pile. 

Loading Type: Combination HA + 30HB Unit
 
Client: Kementerian Kemajuan Luar Bandar & Wilayah  Logo KKLW

S.O.: Kementerian Kemajuan Luar Bandar & Wilayah  Logo KKLW

Consultant: MZMS Consultant

Contractor: JLE Jalinan Ilham Enterprise

Contract Period: 3 Months

Construction Status: Completed 

Proposed new bridge at Kg Kemuning.
Construction of RC abutments at river bank.
Construction of RC abutments.
Transportation of three number of DURA IB650-23m using low loader.
Reversing beam for beam launching.
45 tonnes capacity mobile crane used for beam launching.
Lifting of beam 1.
Positioning beam 2.
Lifting of last beam.
Placing left-in formworks.
All left-in formworks positioned.
Completed bridge.
Completed bridge.
Completed bridge.
Proposed new bridge at Kg Kemuning.
01/14 