Staff Login



2020 Projects

12m Kg. Simpai, Pahang using UHPFRC Bridge

Project: To Build and Upgrade Entrance To Kg. Simpai, Pekan, Pahang Darul Makmur, (Fasa 2)

(Cadangan Membina Dan Menaiktaraf Jalan Masuk Ke Kg. Simpai, Pekan, Pahang Darul Makmur, (Fasa 2) )


GPS Location:   3.217553 N; 103.145294 E (Bridge 1); 3.220677 N; 103.148496 E (Bridge 2)

Structure Type: Single Spans 12m by 6m Wide UHPFRC integral beam-deck system

Superstructure Feature: 4 pieces of DURA® TBG875-12m (per bridge)

Substructure Feature
: Cast in-situ RC abutments

Foundation Feature: 250mm dia. Spun pile (Class B)

Loading Type: HA+ 30 units HB loadings (BD37/01)

Client: JAKOA

S.O.: JKR Pekan, Pahang

Consultant:

Contractor: Goodsons Resources Sdn Bhd

Contract Period:

Construction Status: Completed

    

Project signboard and detail.
Abutments done (220720).
Mobile cranes used for beam launching.
Lifting of first beam.
Lifting of TBG875 beams.
All beams positioned in place.
Beam positioning complete (220720).
08
09
10
11
12
13
14
15
Project signboard and detail.
01/15 
start stop bwd fwd

Single Span of Pedestrian Bridge in Selama, Perak

Project: To Replace Pedestrian Bridge at FT001/671/70, Larut, Matang dan Selama, Perak. D.R.

(Menggantikan Jejantas Di Laluan FT001/671/70 Daerah Larut Matang Dan Selama, Perak D.R.)

GPS Location: 4.787472°N, 100.722296°E

Structure Type: Single Span 28m x 2.8m wide UHPC Bridge System with Precast Staircase

Superstructure Feature:  1 piece of DURA® UTG1200 – 28m

Substructure Feature: RC Columns

Foundation Feature: 300mm Micro-Pile

Loading Type: 5 kPa (BD37/01)

Client: Kementerian Kerja Raya Malaysia

S.O.: Jurutera Daerah, JKR Larut Matang & Selama

Consultant: Jurutera Awam (Jalan), JKR Larut Matang & Selama

Contractor: Belati Wangsa (M) Sdn. Bhd

Contract Period: 18 months

Construction Status: Completed
Project signboard and detail.
Uploading UTG segment to storage yard for PT work.
Preparation of temporary platform.
Aligning first segment (160520).
Aligning last segments.
Tighening the segmental joints temporarily.
Piers ready to receive beam.
Post tensiong work of the UTG birder in progress.
Uploading of UTG1200 to construction site (160620).
Uploading UTG1200 beam on to pole-trailer.
Prepartion on crane setting and ready for beam lifting.
Transportation of beam for beam launching.
UTG1200-28m already positioned on the piers.
Positioning of UTG1200 beam.
UTG1200-30m nicely seated on the peirs (150620).
UTG beam span across the busy road.
Inside view of the U troigh beam.
Completed bridge.
Completed bridge.
Completed bridge.
Completed bridge.
Project signboard and detail.
01/21 
start stop bwd fwd

Lightweight Dura I-Beams Used in Housing Development Project Near Mont Kiara

Project: To Proposed Main Entrance Road (80 Feet Road Reserves) From Front of Lot 2370 to Front of Lot 2368/2363 As well as Adjoining Development Lot, Mukim Batu, Territory Federation of Kuala Lumpur.

(Cadangan Pembinaan Jalan Keluar Masuk Utama ( Rezab Jalan 80 Kaki) Bermula Dari Hadapan Lot 2370 Sehingga Hadapan Lot 2368/2363 Serta Lot – Lot Pembangunan Bersebelahan,  Mukim Batu,  Wilayah Persekutuan Kuala Lumpur)

GPS Location: 3.1688070N, 101.6408440E

Structure Type:. Two Spans UHPFRC Beam Composite In Situ Deck Bridge System  45m x 12.195m

Superstructure Feature:  16 Pieces of Dura IB850 – 22.6m

Substructure Feature: RC Columns

Foundation Feature: 300mm Micro Pile

Loading Type: Comb. of HA-KEL and 45HB Loading (BD37/01)

Client: Qiana Development Sdn. Bhd

S.O.: Pembinaan YSL

Consultant: JPCT

Contractor: Dura Construction Sdn. Bhd

Contract Period: 140 day

Construction Status: Completed
Bridge site.
Construction of substructures in progress.
Pile cap for intermediate pier.
Installation of steel bar for the abutment (160720).
Installation of tempororary formwork for substructure works (160720).
Assembly of scalffold for abutment 2 crosshead.
Crosshead formwork ready for concreting (180820).
Abutment 2.
200t mobile crane setting for beam launching (270820).
Lifting of first beam.
Positioning first beam onto abutment and pier.
8 beams for one span have been positioned.
First 8 nos of I beam has been positioned.
Positioning last beam (270820)
UHPC left-in formwork used between the I beam.
Fixing end diaphragm and deck rebar.
Fixing rebars.
Casting of bridge deck.
Casting of RC deck in progress.
RC deck fully done.
Removal of scarfolding at piers(201020).
Soffit view of the bridge.
Soffit view.
Parapet installed.
Completed bridge.
Bridge site.
01/25 
start stop bwd fwd

DURA Single Span Shallow Beam For JPS Pipe Culvert Replacement

Project: To Replace An Old Bridge At Jalan Kampung Nelayan, Teluk Bahang, Daerah Barat Daya, Pulau Pinang

(Pembinaan Jambatan Baru menggantikan Jambatan Lama Di Jalan Kampung Nelayan, Teluk Bahang, Daerah Barat Daya, Pulau Pinang)

GPS Location: 5.459322 N; 100.208538 E

Structure Type: Single Spans UHPFRC Beam Composite In Situ Deck Bridge System: 10m x 9.9m wide.

Superstructure Feature
: 7 pieces of DURA® Shallow Beams 300 x 400 - 12m with Cast In-Situ RC Deck

Substructure Feature
: 2 nos. of Cast in-situ RC abutments

Foundation Feature
: 250mm x 250mm RC Pile

Loading Type
: HA+KEL or 30 units HB loadings

Client
: JKR Pulau Pinang    jkr pulau pinang
S.O.: JKR Daerah Barat Daya, Pulau Pinang     jkr pulau pinang
Consultant: Perunding Kejuruteraan MK

Contractor: Pembinaan I&R Sdn Bhd

Contract Period: 12 Months

Construction Status: Completed       

Project signboard.
Job Site.
Job Site.
Existing pipe culverts.
Existing pipe culvert.
Demolition work in progress.
Casting of RC300x400 beam.
Mobile crane parking ready for beam launching (190520).
Positioning of first beam.
Seven beams positioned.
Beam launching completed.
Completed bridge.
Completed bridge.
Completed bridge.
Project signboard.
01/14 
start stop bwd fwd

© 2009-2021 by GPIUTMD