First DURA Bridge in the Kingdom of Cambodia

Project: To Construct the First DURA Bridge at Kampot, Cambodia

GPS Location: 10.654308° N; 104.557209°E

Structure Type: Single Spans 26m long by 8.9m Wide Composite Bridge System.

Superstructure Feature
: 2 pieces of DURA® UBG1500-26m with Cast In-Situ RC Deck

Substructure Feature: Cast in-situ RC abutments

Foundation Feature: 300 x 300mm dia. SQ RC. pile (Class B)

Loading Type: Combination of HA+KEL and 45 units HB loadings (BD37/01)

Client: Kampot Cement Co.,Ltd. Cambodia

S.O.: SCG Group Team

Consultant: Construction Solution, The Concrete Products and Aggregate Co.,Ltd.

Contractor: Handan (Cambodia) Construction Co., Ltd

Contract Period: 1st July – 30th December 2019

Construction Status: Completed        

Piling in progress.
Piling in progress.
Unloading UBG1500 segments from a container
Assembly of UBG1500 segment using crawler crane (011119).
Installing strands into the PT ducts.
Aligning segments.
Aligning segments.
Installing strands into the PT ducts.
Stressing of tendons using multi-jack.
Abutments ready to receive beams.
Single lifting method used to positioned the precast beam onto the abutments.
First DURA beam launched into position (081119).
Beam stead on the plinth seating.
Positioning of second beam.
Completion of beam launching.
Completed first UHPC road bridge in Cambodia.
Piling in progress.