Pembinaan Lencongan Sungai Baru (CH0 - CH12600) Dan Menaiktaraf Sungai Anak Bukit (CH0 - CH1750) Serta Kerja-Kerja Berkaitan. Racangan Tebatan Banjir Sungai Kedah/Anak Bukit, Kedah. (Light Traffic Bridge).(The Construction of New River Detour (CH0-CH12600) and Upgrading of Sungai Anak Bukit (CH0-CH1750) and Other Related Works. Flood Mitigation Plan at Sungai Kedah/Anak Bukit, Kedah. (Light Traffic Bridge).Nos. of Bridge: 13
2017
Completed Project
Malaysia
4.71685 N, 101.55253 E (Bridge 1); 4.718020 N, 101.55253 E (Bridge 2); 4.72700 N, 101.53364 E (Bridge 3); 4.730966 N, 101.51705 E (Bridge 4); 4.74706 N, 101.48913 E (Bridge 5); 4.747055 N, 101.48700 E (Bridge 6)
Single Span 12 and 18m x 6m wide Composite Bridge System.
4 pieces of DURA® IB650-12m per bridge (Bridge 1 to 5) and 4 pieces of DURA® IB650-18m (Bridge 6)
2 nos. of cast in-situ RC abutments per bridge
steel fiber reinforced mass concrete
HA + KEL loading + 30 Units HB Loadings (BD37/01)
JAKOA

Felcra Berhad

Jurutera Perunding Marak Bersekutu
Chengaljati Sdn Bhd
29 months
Completed