Construction of Access Controlled Nagpur - Mumbai Super Communication Expressway (Maharashtra Samruddhi Mahamarg) In The State Of Maharashtra On Epc Mode For Package 11, From Km. 502+698 To Km. 532+094 (Section - Village Dhotre To Village Deride Korhale) In Dist Ahmednagar.
2023
Completed Project
India
19.843307 N, 74.478077 E
1 span x 52.860 m long (total 52.860 m), Major Bridge; 1 span x 53.860 m long (total 53.860 m), Major Bridge
Simply Supported Four (4) UHPC UBG2250 Girders for each span.
RC Stem wall
Open foundation for walls.
IRC Class Loadings.
Maharashtra State Road Development Corporation
Raj infrastructures.
1 Years
On-going
Long Span Structures Pvt. Ltd.
Indian Institute of Science Bengaluru, Karnataka