To Proposed Main Entrance Road (80 Feet Road Reserves) From Front of Lot 2370 to Front of Lot 2368/2363 As well as Adjoining Development Lot, Mukim Batu, Territory Federation of Kuala Lumpur.(Cadangan Pembinaan Jalan Keluar Masuk Utama ( Rezab Jalan 80 Kaki) Bermula Dari Hadapan Lot 2370 Sehingga Hadapan Lot 2368/2363 Serta Lot – Lot Pembangunan Bersebelahan, Mukim Batu, Wilayah Persekutuan Kuala Lumpur)
2020
Completed Project
Malaysia
3.1688070N, 101.6408440E
Two Spans UHPFRC Beam Composite In Situ Deck Bridge System 45m x 12.195m
16 Pieces of Dura IB850 – 22.6m
RC Columns
300mm Micro Pile
Comb. of HA-KEL and 45HB Loading (BD37/01)
Qiana Development Sdn. Bhd
Pembinaan YSL
JPCT
Dura Construction Sdn. Bhd
140 day
Completed