Kerja-Kerja Membina Dan Pencegah Banjir Sungai Kurau Dari Hulu kolam Bukit Merah Ke Pondok Tanjung Sepanjang 8.4 km Serta Kerja Kerja Lain Yang Berkaitan, Dearah Kerian, Perak Darul Ridzuan (Bridge 1 Sg. Kurau CH.3336.5)
2014
Completed Project
Malaysia
Single span 50m x 4.8m wide UHPdC U beam composite bridge
1 pieces of DURA® UBG1750-50m topped with 180mm thk in-situ RC deck slab
450mm dia. Spun Pile (Class B)
Full HA+30 unit HB loadings
JKR Perak
Dura Technology Sdn Bhd
Aspasia Construction & Development S/B
Completed