Construct of a New Bridge Crossing Perak River, Batu 6, Kampung Rhui, Bandariang, Gerik, Hulu Perak District, Perak D.R.(Jambatan Menyeberangi Sungai Perak, Batu 6, Kampung Rhui, Bandariang, Gerik, Daerah Hulu Perak, Perak D.R.)
2015
Completed Project
Malaysia
5.45040N, 101.18660E
Single Span 100m long by 5.0m wide (MTB-R1) UHPC box brigde system.
1 piece of DURA® Box Bridge Girder BBG4000-100m
24 nos. 300mm dia. micropiles per Abutment
Full HA + 30units HB loading (BD37/01) + 5 kPa Pedestrian
JKR Perak
Jurutera Perunding Concrete Technology
ZA (Malaysia) Sdn Bhd (Class B)
24 months